Hit enter to search
Highways & Local Government

Upper Don Flood Alleviation Scheme

LOCATION Sheffield CLIENT Sheffield County Council START DATE October 2022 CAPABILITIES
  • Flood Alleviation
  • Design
  • Construction
  • Demolition
  • Concrete works
  • Temporary works
  • Steel works
  • Piling

Project Scope

UPPER DON FLOOD ALLEVIATION SCHEME (PHASE ONE) – DESIGN AND CONSTRUCTION

The project involved the design and construction of linear flood defences across 15 sites along both banks of the river Loxley from Malin bridge to the confluence of the rivers Loxley and Don. The project is designed to alleviate flooding in the Hillsborough, Malin Bridge and Owlerton areas of Sheffield.

 

UPPER DON FLOOD ALLEVIATION SCHEME (PHASE ONE) – FLOOD ALLEVIATION WORKS

Keltbray’s main scope of works included the construction of new structural concrete retaining walls (1.5km long); Raising and strengthening of existing walls, including the installation of steel beams to counteract flood pressures; Ground raising (clay earthwork bunds, 1m x 60m); Embankment construction, including brick clad walls with copings along the whole section of defences; Utilised a bulk bag dam to enable works on retaining walls; Construction of bridge parapets along the Penistone Road Bridge; Installation of sheet pile walls rather than demolition of pre-existing buildings; Vibration free piling used throughout installation of the sheet piles; Demolition of existing balconies, and installation of new balconies with demountable flood defences; Installation of demountable flood barriers on Rudyard Mews, approximately 40m in length total; And removal of an existing weir to assist with works.

 

UPPER DON FLOOD ALLEVIATION SCHEME (PHASE ONE) – ECOLOGY

Working with River Stewardship Company, Natural England, and the Environment Agency, we phased the project to minimise disruption to aquatic life, ensuring all necessary permits were in place.

Environmental efforts included protecting fish, crayfish, and nesting birds, relocating bats, and addressing an unidentified badger sett under Regent Court car park. Consulting BWB, we amended the design of the culvert installing a concrete slab, headwall, and pipe for safe badger access.

Additionally, we managed invasive plants like Japanese Knotweed and Himalayan Balsam via spraying and injection methods.

 

UPPER DON FLOOD ALLEVIATION SCHEME (PHASE ONE) – CARBON REDUCTION

To power our on-site welfare facilities for our site team we engaged with Aggreko to deliver 2x 60kVa generators, equipped with monitoring technology to ensure efficient operation and proactively monitor mechanical faults.

Upon review, Aggreko and ourselves agreed to remove one generator and replace with a 55kW lithium-ion battery to provide a hybrid solution to our power requirements. This allowed for dual use – the generator would handle peak energy performance whilst the battery would manage the lower loads.

During each four-week period the solution was on site, we were able to make savings of approximately 2.7 litres per hour compared to a standard generator set-up, whilst also lowering noise levels to the surrounding area. In addition, we were able to make a reduction of 4.8 tonnes of carbon emissions over these periods.

 

Key Challenges and Solutions

Third party assets

  • Challenge: Managing third party owned land and businesses surrounding the project
  • Solution: Amended original flood defence plans which involved demolishing industrial buildings, avoiding costly and disruptive practice. Avoided this by installing sheet pile walls and using a Giken silent piler significantly reducing noise and vibration, crucial in the environmentally sensitive area, further mitigating impacts.

Ecology on site

  • Challenge: Managing a wide scope of ecological constraints and adapting to unexpected badger sett.
  • Solution: Developed plans in line with our Environmental Management Plan (EMP) to implemented measures to manage ecology safely, mitigate loss of biodiversity.

Working in water

  • Challenge: Working in and around water resulting in the need to dam the river temporarily to facilitate construction. Further challenges posed from traversing sedimentary materials.
  • Solution: Careful planning and actioned the amendment of damming methods and subcontractor methods to accommodate the limited working room and constraints caused by damming off the river.